To See Committed Costs in Beanworks
Go to the Committed tab of the PO module and look at the remaining column.
If you don't see this column:
1. Click the cog icon above the headers.
2. Select 'Remaining' and move it over to the left column. If you already have 9 items in the left column, you'll need to remove one first before adding 'Remaining'.
3. Select 'Save'. You can now easily see in the amount left in the PO.